Knight Energy’s 2017 Chapter 11 reorganization reached effectiveness, and the court entered a final decree Dkt. 1088 on June 27, 2019. The decree is the latest identified milestone; no further material step is established.
No published developments to display.
| Month | Entries |
|---|---|
| August 2017 | 222 |
| September 2017 | 151 |
| October 2017 | 111 |
| November 2017 | 93 |
| December 2017 | 39 |
| January 2018 | 17 |
| February 2018 | 12 |
| March 2018 | 63 |
| April 2018 | 80 |
| May 2018 | 52 |
| June 2018 | 48 |
| July 2018 | 53 |
| August 2018 | 37 |
| September 2018 | 32 |
| October 2018 | 33 |
| November 2018 | 11 |
| December 2018 | 12 |
| January 2019 | 1 |
| February 2019 | 0 |
| March 2019 | 0 |
| April 2019 | 7 |
| May 2019 | 3 |
| June 2019 | 12 |
Case facts and filing dates come from court records.Case docket on PACER