Quality Construction & Production’s March 2018 Chapter 11 proceeded to confirmation of a joint reorganization plan, followed by an order granting a final decree Dkt. 941 on December 31, 2019. The court confirmed the modified plan in May 2019; no subsequent material milestone is identified in the filings summarized here.
Quality Construction & Production, LLC’s Chapter 11 reached a final decree order on December 31, 2019, when the court granted Energy Services Note Acquisition’s motion Dkt. 941. The court had confirmed the modified sixth amended joint plan of reorganization Dkt. 758 on May 22, 2019. No subsequent material milestone is identified in the filings summarized here.
The Louisiana offshore oil-and-gas services contractor filed for Chapter 11 on March 16, 2018 Dkt. 1, alongside affiliated debtors. During the case, the court authorized use of cash collateral to support operations; its April 2019 final order Dkt. 672 provided for budgeted use and replacement liens for Energy Services, the assignee of MidSouth Bank’s interests.
The debtors initially proposed their own reorganization plan. Energy Services Note Acquisition and CAC Services later sponsored the sixth amended joint plan Dkt. 704, which was modified before confirmation. Energy Services filed a notice concerning the effective date Dkt. 759 on May 23, 2019.
Sources
- Dkt. 1Chapter 11 Voluntary Petition Non-Individual. Fee Amount Due $1717 Filed by Thomas E. St. Germain of Weinstein Law Firm on behalf of Quality Construction & Production, LLC. Attorney Disclosure Statement due by 03/30/2018. Employee Income Record for Debtor due by 03/30/2018. Schedule A/B due by 03/30/2018. Schedule D due by 03/30/2018. Schedule E/F due by 03/30/2018. Schedule G due by 03/30/2018. Schedule H due by 03/30/2018. Statement of Financial Affairs due by 03/30/2018. Summary of Assets and Liabilities due by 03/30/2018. Incomplete Filings due by 03/30/2018. Disclosure Statement Chapter 11 due by 07/16/2018. Chapter 11 Plan due by 07/16/2018. (St. Germain, Thomas) (Entered: 03/16/2018)Filed Mar 16, 2018Mar 16, 2018
- Dkt. 672Final Order Granting Use of Cash Collateral (Re: 99 Motion to Use Cash Collateral filed by Debtor Quality Construction & Production, LLC) (katc) (Entered: 04/08/2019)Filed Apr 8, 2019Apr 8, 2019
- Dkt. 704Sixth Amended Joint Plan of Reorganization (Re: 692 Amended Chapter 11 Plan) Filed by Howard Marc Spector of Spector & Johnson, PLLC on behalf of CAC Services, LLC, Energy Services Note Acquisition, LLC (Spector, Howard) CLERK'S ENTRY - MODIFIED TO STATE COMPLETE TITLE OF DOCUMENT 4/16/2019 (katc). (Entered: 04/16/2019)Filed Apr 16, 2019Apr 16, 2019
- Dkt. 758Order Confirming Sixth Amended Joint Plan of Reorganization, As Modified (Re: 755 Sixth Amended Chapter 11 Plan Before Confirmation as Modified by ESNA) Filed on 5/22/2019 (katc) (Entered: 05/22/2019)Filed May 22, 2019May 22, 2019
- Dkt. 759Notice on Effective Date Filed by Howard Marc Spector on behalf of Energy Services Note Acquisition, LLC (Spector, Howard) (Entered: 05/23/2019)Filed May 23, 2019May 23, 2019
- Dkt. 941Order Granting (Re: 923 Motion for Final Decree filed by Creditor Energy Services Note Acquisition, LLC) (katc) (Entered: 12/31/2019)Filed Dec 31, 2019Dec 31, 2019