SCI Direct LLC: Chapter 11 case summary
ElevenFlo ·
SCI Direct’s Chapter 11 plan became effective on April 18, 2019, following confirmation in February, according to the effective-date notice Dkt. 459. The case moved to implementation of the joint reorganization plan proposed by the debtors and the unsecured creditors’ committee; no later milestone is identified.
SCI Direct LLC’s Chapter 11 plan became effective on April 18, 2019, as reported in the effective-date notice Dkt. 459. The court had confirmed the first amended joint plan on February 25, 2019, in the confirmation order Dkt. 434.
SCI Direct filed for Chapter 11 on August 7, 2017, alongside Suarez Corporation Industries, Retail Partner Enterprises and Media Service Corporation. The amended disclosure statement Dkt. 396 says the debtors financed operations through credit agreements with Nancy Suarez and reports her petition-date secured claim as $18,708,433.30.
During the case, the court authorized use of cash collateral and postpetition financing in the final financing order Dkt. 110. The debtors and the official committee of unsecured creditors subsequently proposed the first amended joint plan Dkt. 395, which provided for reorganization and addressed Suarez’s secured claims. Following effectiveness, the plan moved to implementation; no later milestone is identified.
Sources
- Dkt. 110Stipulation and Final Order Granting Motion of the Debtors in Possession: (A) Authorizing the Debtors' Use of Cash Collateral Pursuant to Section 363 of the Bankruptcy Code; (B) Authorizing the Debtors to Obtain Post-Petition Financing Pursuant to Section 364 of the Bankruptcy Code; (C) Providing Adequate Protection and Granting Superpriority Claims; and (D) Approving and Authorizing Debtors to Enter into Certain Related Loan DocumentsFiled Oct 12, 2017Oct 12, 2017
- Dkt. 395First Amended Joint Plan of Reorganization of the Debtors and the Official Committee of Unsecured Creditors (Filed by Debtor SCI Direct LLC)Filed Jan 17, 2019Jan 17, 2019
- Dkt. 396Disclosure Statement for First Amended Joint Plan of Reorganization of the Debtors and the Official Committee of Unsecured Creditors (Filed by Debtor SCI Direct LLC)Filed Jan 17, 2019Jan 17, 2019
- Dkt. 434Findings of Fact, Conclusions of Law and Order Confirming the First Amended Joint Plan of ReorganizationFiled Feb 25, 2019Feb 25, 2019
- Dkt. 459Notice of Effective Date of First Amended Joint Plan of Reorganization (Filed by Debtor SCI Direct LLC)Filed Apr 18, 2019Apr 18, 2019