UPG secures $6.477 million Firehorse financing as court proposes ruling on electrical sale procedures without a hearing
ElevenFlo ·
UPG’s November 16 financing order authorized $6.477 million in new money from Firehorse without rolling up its $4.98 million bridge loan Dkt. 408. Two sales won approval November 13. For the Electrical Debtors, TRM bid $6.5 million Dkt. 386. The court proposed entering revised bidding procedures without the November 20 hearing unless a party requested to be heard by 5 p.m. CT November 19 Dkt. 429 · p. 1. The proposed bid deadline is December 2 at 4 p.m. CT Dkt. 425 · p. 6.
Jump to section
The order caps a week in which the court approved two asset sales and six UPG Electrical entities joined the case.
On November 16, 2026, the court entered a final order. It authorizes UPG Enterprises LLC and its affiliated debtors to borrow from Firehorse Capital LLC, an affiliate of UPG's owners, and to use their lenders' cash collateral Dkt. 408. The order states aggregate DIP commitments of $8,477,000 in principal, consisting solely of new-money term loan commitments of up to $6,477,000. The full new-money amount is available on entry, subject to conditions precedent, borrowing limits and the order's milestones Dkt. 408 · p. 2. No part of the facility rolls up Firehorse's $4,984,214.59 prepetition bridge loan, which remains a prepetition claim secured only by its existing liens. Objections not otherwise resolved were overruled Dkt. 408.
Three days earlier, the court approved two sales. Metalex LLC is selling its business assets to Alabama Metal Industries Corporation (AMICO) for $6.5 million in cash, subject to adjustment. Metal Acquisition, Inc. holds a $5.65 million backup bid Dkt. 400. Chicago Steel Holdings LLC and Lexington Steel LLC are selling their assets to The Mill Steel Co. for a $4 million base price plus inventory value Dkt. 401. The filings through November 16 do not report that either sale has closed.
The case has also grown. Six UPG Electrical entities filed chapter 11 petitions on November 12, 2026 Dkt. 387 · p. 4. On November 13 the court ordered their cases jointly administered under the UPG Enterprises case, for procedural purposes only and without substantive consolidation Dkt. 392. The debtors propose to sell substantially all Electrical Debtor assets to TRM Equity Fund II LP as stalking horse, at a $6.5 million headline price. On November 18 the court said it intended to enter the revised procedures without holding the November 20 hearing. A party wishing to be heard had to file a notice by 5 p.m. CT on November 19 Dkt. 429 · p. 1. The proposed schedule has bids due December 2, an auction on December 3 if needed, and a requested sale hearing on December 8 Dkt. 410.
The final order dropped the bridge roll-up and limited the lender's reach into estate claims
Firehorse's financing was approved in three steps. The September 28 interim order authorized up to $6.083 million in new-money commitments and made $2 million available. It expressly withheld approval of a proposed roll-up of Firehorse's prepetition bridge debt Dkt. 61. The October 16 hearing agenda adjourned the final financing hearing, then set for October 20, to a date to be determined Dkt. 138. A second interim order on November 12 added $500,000 of availability, for a total of $2.5 million, and set the final hearing for that afternoon Dkt. 378. The final order raised the new-money commitment to $6.477 million Dkt. 408 · p. 2.
- $2.0M
- $2.5M
- $6.477M
Show the numbers
| Order | New money available |
|---|---|
| Interim order, Sept. 28, 2026 | $2.0M |
| Second interim order, Nov. 12, 2026 | $2.5M |
| Final order, Nov. 16, 2026 | $6.477M |
Source: interim order Dkt. 61; second interim order Dkt. 378; final order Dkt. 408 · p. 2
These amounts are borrowing capacity and do not show how much cash has been drawn. Borrowings must follow a 13-week revised budget and be held in a segregated DIP loan account. Firehorse's exit fee is calculated on actual postpetition borrowings, not on the full commitment Dkt. 408.
The DIP liens cover all debtor assets except avoidance actions, other estate claims and commercial tort claims. They reach the proceeds of those claims only up to the new money Firehorse actually funds, and those proceeds do not secure the bridge loan or other prepetition debt. The DIP liens are junior to the prepetition lenders' liens and replacement liens, and they do not prime the bridge liens. Subject to the order's conditions, Firehorse may credit bid the full bridge and DIP obligations. For avoidance actions and other estate claims, it may credit bid only up to the new money it has funded Dkt. 408.
The prepetition secured lenders, White Oak and Wintrust, consented to the use of cash collateral. They receive replacement liens, section 507(b) claims, default-rate interest paid in cash under the budget, and fees and expenses. Each lender's borrowing group reports weekly and must keep availability at no less than 85% of its forecast. Firehorse receives no separate adequate protection for the bridge loan Dkt. 408.
The order waives section 506(c) surcharge rights, the section 552(b) equities-of-the-case exception and marshaling. It also releases the prepetition secured parties and Firehorse, subject to challenge. Parties in interest have 75 days from the September 28 interim order to bring a challenge. The creditors' committee, formed October 5, 2026, has 60 days from its formation. The investigation budget is $50,000, up from $25,000 in the interim order Dkt. 408 Dkt. 61. After a trigger notice, the carve-out caps fees at $100,000 for the debtors' professionals and $50,000 for committee professionals, plus up to $50,000 for a chapter 7 trustee Dkt. 408.
The financing is tied to sale milestones:
- entry of an order approving TRM's financing for the electrical business by November 13;
- receipt of released Wintrust cash collateral into the DIP loan account by November 20;
- closing of the TRM sale, with its net proceeds funded into that account, by December 8.
A missed milestone is an event of default unless extended or waived in writing. Before terminating on that basis, Firehorse must give notice and consult for at least two business days. Remedies then follow a five-business-day notice period Dkt. 408.
The U.S. Trustee and landlords had objected to the roll-up and to liens on estate claims
The U.S. Trustee did not oppose UPG obtaining financing. Its limited objection targeted three requests: the roll-up, liens on avoidance actions and on claims against the lender or its principals, and a waiver of the estates' surcharge rights under section 506(c). The Trustee argued that the bridge lending and its use should be investigated before the debt received postpetition administrative priority. Those were objections to requested relief, not findings that the lending was improper Dkt. 105.
The ARG landlord entities raised a related concern. They alleged that estate claims against the owners could become collateral for the owners' own lending vehicle. Their objection also challenged the proposed releases, limits on investigating lender claims, and Firehorse's influence over sale and plan milestones. They asked the court to deny final approval unless the terms were changed Dkt. 111.
Sordillo, the chief restructuring officer, presented the debtors' position differently. He stated that the financing was negotiated at arm's length and that its terms are reasonable under the circumstances. He said access to the facility was needed to preserve operations and going-concern value Dkt. 17.
The final order omits the roll-up. It keeps the estate claims themselves out of Firehorse's collateral and limits the DIP liens on their proceeds to the new money actually funded. It keeps the section 506(c) waiver that the Trustee opposed, and it keeps the releases, subject to the challenge period. Any objections not otherwise resolved were overruled Dkt. 408.
Metalex and the Chicago and Lexington steel units have court-approved buyers
UPG entered chapter 11 after an extensive marketing effort. According to Sordillo, SC&H contacted approximately 267 prospective buyers. Of those, 86 signed confidentiality agreements and 10 submitted letters of interest. The highest-value indications required a chapter 11 sale. His declaration describes the intended outcome as asset sales followed by an orderly wind-down Dkt. 17.
The September 25 bidding-procedures motion proposed an October 28 bid deadline, a November 2 auction, a November 5 sale hearing and closing by November 19. It allowed for one or more stalking-horse bidders and separate sales Dkt. 49. The court later entered bidding and contract-assumption procedures, which the debtors now ask to extend to the Electrical Debtors Dkt. 386.
| Seller | Buyer | Consideration | Other terms |
|---|---|---|---|
| Metalex LLC | Alabama Metal Industries Corporation (AMICO) | $6.5 million cash, subject to adjustment, plus assumed liabilities and cure amounts | $5.65 million backup bid from Metal Acquisition, Inc., held open through five business days after closing |
| Chicago Steel Holdings LLC and Lexington Steel LLC | The Mill Steel Co. | $4 million base plus inventory value, subject to adjustment; $400,000 deposit | Closing due by November 15, 2026 under the agreement; proceeds paid to the prepetition secured parties |
Source: AMICO sale order Dkt. 400; Mill Steel sale order Dkt. 401
Each sale draws on the collateral of a different prepetition lender. Chicago Steel Holdings and Lexington Steel are White Oak borrowers Dkt. 17 · p. 9. Metalex is a Wintrust borrower Dkt. 17 · p. 10.
The Mill Steel order directs that sale proceeds be paid to the respective prepetition secured parties. Until then the proceeds are held in trust, and the debtors cannot use them without those parties' written consent. The order preserves estate claims for fraud or breach of fiduciary duty. It does not decide the allowance, amount, validity or priority of lender claims or liens Dkt. 401.
Under the AMICO order, liens and other interests attach to the sale proceeds with their prior priority. The sale covers the Libertyville facility interests, equipment, inventory, receivables, intellectual property and designated contracts, but not cash Dkt. 400. Both orders take effect immediately and waive the stays under Bankruptcy Rules 6004(h) and 6006(d) Dkt. 400 Dkt. 401.
The electrical business entered the case behind a $6.5 million TRM stalking-horse bid
When UPG filed in September, its announcement said the cases covered certain U.S. operations. It said they excluded international operations, UPG Electrical and UPG Electrical's subsidiaries prnewswire.com: UPG filing announcement (outside source). The announcement also identified Epiq as claims and noticing agent and directed readers to the case website dm.epiq11.com: UPG case website (outside source).
The Electrical Debtors process and fabricate electrical-grade steel and laminations for industrial, power-generation, automotive and other markets. Their facilities are in Elk Grove Village, Illinois, and Monroe, Wisconsin. Mapes & Sprowl Steel LLC supplies substantially all of their steel. Sordillo attributes their decline to customer losses, constrained working capital, limited inventory and increased spot purchasing. They were marketed alongside the original debtors. An attempted Article 9 foreclosure sale fell through when the prospective buyer could not reach agreement with the landlord. The debtors then agreed with TRM on a section 363 going-concern sale Dkt. 389.
TRM signed the stalking-horse agreement on November 12. Its $6.5 million headline price is made up of cash, assumed liabilities and a credit bid of TRM's DIP claims. The debtors seek a 3% break-up fee and expense reimbursement of up to $200,000 for TRM. A competing bid must cover all purchased assets and offer cash at least equal to the purchase price plus the bid protections and $250,000. It must also include a 10% cash deposit Dkt. 386. If no other qualified bid arrives for particular assets, the debtors say they will not auction those assets and will designate TRM's bid as successful Dkt. 410. Contract counterparties have until December 1 to object to proposed cure amounts Dkt. 411.
The Electrical Debtors also asked for $2,349,833.49 of new-money DIP financing in two tranches. TRM would lend up to $1,754,193.99: $1.3 million for case costs and $454,193.99 toward paying off FGI Worldwide LLC. Firehorse would lend $595,639.50 on a subordinated basis to pay the rest of the FGI payoff Dkt. 387 · p. 6. The proposed interest rate is 15%, paid in kind weekly, rising to 17% on default. TRM would also receive a 5% closing fee on the first tranche and a fee of 1.25 times the first-tranche amount actually funded. The proposed interim order sets maturity at December 9, 2026, with earlier triggers, including failure to enter a final order within 21 days Dkt. 387. The revised four-week budget forecasts $1.637 million of receipts, $2.936 million of disbursements and $1.3 million of draws Dkt. 394.
The November 16 interim financing order made up to $1,889,833.49 available to the Electrical Debtors on an interim basis Dkt. 413 · p. 1. It set a final financing hearing for December 1 at 2 p.m. CT and objections for November 24 at 4 p.m. CT. The court may enter a final order without a hearing if no timely responses or objections are filed and served Dkt. 413 · p. 49. The November 13 amended agenda had listed the financing motion as going forward Dkt. 399. Firehorse's final order made entry of the TRM financing order by November 13 one of its milestones Dkt. 408.
White Oak's $50.4 million revolver is most of the identified debt
Four secured facilities carry approximately $63.4 million of identified debt. That figure mixes principal-and-interest balances with a note's original principal and includes debt owed by non-debtor affiliates. It is not a complete total of the debtors' obligations.
White Oak Commercial Finance, LLC is agent on a $90 million revolver due December 31, 2028. The borrowers are debtors Maksteel USA LLC, Chicago Steel Holdings LLC and Lexington Steel LLC and non-debtor Maksteel Holdings LLC. Debtor UPG Flat Roll Group LLC and non-debtor Maksteel Holding Corp. are guarantors Dkt. 17 · p. 9. Sordillo reported approximately $50,424,614.73 of principal and interest outstanding at the petition date, plus other obligations, secured by first-priority liens. The balance includes amounts attributable to Maksteel Holdings ULC, the non-debtor's Canadian subsidiary Dkt. 17 · p. 10.
Schaumburg Bank & Trust Company, N.A. is agent on the Wintrust facility, entered August 22, 2022. Its borrowers are debtors Metalex, LLC, National Metalwares, L.P., UPG Fabrication LLC, National Metalwares Holdings LLC and Sidecar NM LLC Dkt. 17 · p. 10. Approximately $7,520,357.86 of principal and interest was outstanding, secured by first-priority liens on the borrowers' personal property Dkt. 17 · p. 11.
The owners provided the bridge loans through Firehorse to fund an independent governance process and restructuring advisers Dkt. 17 · p. 9. They are documented by a fourth amended and restated promissory note dated September 17, 2026, for $4,984,214.59. All of the debtors and certain non-debtor affiliates are obligors. The loans are secured by all debtor assets but subordinated to the White Oak and Wintrust liens under an intercreditor agreement Dkt. 17 · p. 11.
On the electrical side, FGI provided a revolver of up to $25 million, due August 25, 2028. Five Electrical Debtors are borrowers, and UPG Electrical Holdings LLC is guarantor. At the November 12 petition date, $454,193.99 of principal and interest was outstanding. A $250,000 termination fee and $270,639.50 of attorneys' fees and costs were also owed Dkt. 387 · p. 10. The proposed electrical financing would pay FGI up to $974,833.49 and fund a separate $75,000 expense reserve Dkt. 387.
- First-priority liens
- Junior to White Oak and Wintrust
- White Oak revolverFlat Roll debtors and non-debtor Maksteel entities$50.42M
- Wintrust facilityFabrication debtors$7.52M
- FGI revolverElectrical Debtors$0.45M
- Firehorse bridge noteAll debtors and certain non-debtor affiliates$4.98M
Show the numbers
| Facility | Borrowers | Amount |
|---|---|---|
| White Oak revolver | Flat Roll debtors and non-debtor Maksteel entities | $50.42M |
| Wintrust facility | Fabrication debtors | $7.52M |
| FGI revolver | Electrical Debtors | $0.45M |
| Firehorse bridge note | All debtors and certain non-debtor affiliates | $4.98M |
Source: first-day declaration Dkt. 17; Electrical Debtors' financing motion Dkt. 387 · p. 10
Below the secured debt, Sordillo reported approximately $530,000 of priority claims and $11 million of trade and other unsecured debt at the petition date. Pending litigation claims exceeded $30 million and may overlap with trade claims Dkt. 17. The lead petition's consolidated list of the 30 largest unsecured claims is led by Global Net Lease Operating Partnership, L.P. at $962,375.18 and thyssenkrupp Materials N.A. at $554,681.36 Dkt. 1.
The lead petition's balance-sheet ranges are not consolidated group figures. UPG Enterprises LLC estimated assets of $1,000,001 to $10 million and liabilities of $10,000,001 to $50 million Dkt. 1. Sordillo separately estimated consolidated debtor book-value assets above $75 million and liabilities above $100 million. The figures cover different scopes, and book value does not establish sale proceeds or creditor recoveries Dkt. 17.
Contract losses, lender reserves and payroll strain preceded the filing
UPG Enterprises LLC is an Oak Brook, Illinois holding company Dkt. 1. Its debtors operate a Flat Roll group, which processes and sells steel, and a Fabrication group, which makes steel products and components Dkt. 17. The original debtors filed chapter 11 petitions on September 22 and 23, 2026 Dkt. 17 · p. 4.
Sordillo attributes UPG's liquidity problems to operating setbacks and tighter borrowing availability. Terminating a loss-making automotive contract cost more than $15 million, and sales fell after leadership changes. The prior lender also ended its relationship with UPG, which required a refinancing. Borrowing-base reserves imposed by the lenders tightened liquidity further. By the filing, some key suppliers required cash in advance or had put business on hold. The debtors were struggling to meet payroll for approximately 282 employees Dkt. 17.
The owners reportedly contributed nearly $60 million to the debtors and the non-debtor operating group since 2024. Forbearance agreements starting in November 2025 allowed continued borrowing but did not cover non-operating expenses. In June 2026, an independent manager and a special committee were appointed to oversee the restructuring. The declaration also describes more than 20 pending lawsuits involving lease, injury and vendor disputes Dkt. 17.
Sources
- Dkt. 1UPG Chapter 11 PetitionFiled Sep 22, 2026Sep 22, 2026
- Dkt. 17Sordillo DeclarationFiled Sep 23, 2026Sep 23, 2026
- Dkt. 49Proposed Asset Sale ProcessFiled Sep 25, 2026Sep 25, 2026
- Dkt. 61Interim DIP OrderFiled Sep 28, 2026Sep 28, 2026
- Dkt. 105Trustee’s Limited DIP ObjectionFiled Oct 13, 2026Oct 13, 2026
- Dkt. 111ARG Entities’ Financing ObjectionFiled Oct 13, 2026Oct 13, 2026
- Dkt. 138October 20 Hearing AgendaFiled Oct 16, 2026Oct 16, 2026
- Dkt. 378Second Interim Financing OrderFiled Nov 12, 2026Nov 12, 2026
- Dkt. 386Electrical Debtors Sale ProceduresFiled Nov 12, 2026Nov 12, 2026
- Dkt. 387Electrical Debtors DIP MotionFiled Nov 13, 2026Nov 13, 2026
- Dkt. 389Electrical Debtors’ Supplemental DeclarationFiled Nov 13, 2026Nov 13, 2026
- Dkt. 392Joint Administration OrderedFiled Nov 13, 2026Nov 13, 2026
- Dkt. 394Revised DIP Budget NoticeFiled Nov 13, 2026Nov 13, 2026
- Dkt. 399Amended Hearing AgendaFiled Nov 13, 2026Nov 13, 2026
- Dkt. 400Metalex Asset Sale ApprovedFiled Nov 13, 2026Nov 13, 2026
- Dkt. 401Mill Steel Asset SaleFiled Nov 13, 2026Nov 13, 2026
- Dkt. 408Final Financing and Cash Collateral OrderCited at p. 2 · Filed Nov 16, 2026Nov 16, 2026
- Dkt. 410Electrical Debtors Sale NoticeFiled Nov 16, 2026Nov 16, 2026
- Dkt. 411Potential Contract AssignmentsFiled Nov 16, 2026Nov 16, 2026
- Dkt. 413Interim DIP Financing OrderFiled Nov 16, 2026Nov 16, 2026
- Dkt. 425Revised Sale Order NoticeCited at p. 6 · Filed Nov 18, 2026Nov 18, 2026
- Dkt. 429Order on Proposed OrderCited at p. 1 · Filed Nov 18, 2026Nov 18, 2026
- WebUPG filing announcementprnewswire.com · Outside source
- WebUPG case websitedm.epiq11.com · Outside source