NorthEast Gas Generation, LLC: Chapter 11 case summary
ElevenFlo ·
NorthEast Gas Generation’s Chapter 11 case was closed on March 22, 2021, when the court entered the final decree Dkt. 412 closing the case and terminating claims and noticing services.
The company filed its Chapter 11 petition Dkt. 1 on June 18, 2020. Indirectly owned by Talen Energy, it owned two natural gas-fired generating facilities: a 1,080 MW plant in Athens, New York, and a 360 MW plant in Charlton, Massachusetts. The first-day declaration Dkt. 9 attributed the liquidity crisis to historically low natural gas prices, reduced electricity demand and pandemic-related economic pressures. After a series of forbearance agreements, the first-lien agent accelerated the debt on June 15, 2020; the energy manager issued termination notices for the energy management agreements two days later.
The court’s July 17, 2020 final financing order Dkt. 111 authorized a $39,033,843.31 DIP term-loan commitment, a separate $966,156.69 emergency bridge facility and use of cash collateral. The restructuring proceeded to the confirmation order Dkt. 354 entered December 18, 2020, approving the Second Amended Joint Chapter 11 Plan for NorthEast Gas Generation and its affiliated debtors. The notice of effectiveness Dkt. 360 filed December 22, 2020 reported plan effectiveness and established a deadline for general administrative expense claims, preceding the March 2021 closure.
Sources
- Dkt. 1Chapter 11 Voluntary Petition . Fee Amount $1717. Filed by NorthEast Gas Generation, LLC.Filed Jun 18, 2020Jun 18, 2020
- Dkt. 9First Day DeclarationFiled Jun 18, 2020Jun 18, 2020
- Dkt. 111Order (FINAL) Pursuant to 11 U.S.C. §§ 105, 361, 362, 363, 364, and 507, and Fed. R. Bankr. P. 2002, 4001 and 9014, (I) Authorizing the Debtors to Obtain Postpetition Financing, (II) Authorizing Use of Cash Collateral, (III) Granting Liens and Super-Priority Claims, (IV) Granting Adequate Protection, and (V) Granting Related Relief (related document(s)10, 34, 108) Signed on 7/17/2020.Filed Jul 17, 2020Jul 17, 2020
- Dkt. 354Order Confirming the Second Amended Joint Chapter 11 Plan of Northeast Gas Generation, LLC and its Affiliated Debtors(related document(s)178, 230, 347, 351) Signed on 12/18/2020. (Attachments: # 1 Exhibit A # 2 Exhibit B # 3 Exhibit C)Filed Dec 18, 2020Dec 18, 2020
- Dkt. 360Notice of Effective Date (Notice of (I) Effective Date and Entry of Order Confirming the Second Amended Joint Chapter 11 Plan of Northeast Gas Generation, LLC and Its Affiliated Debtors and (II) Establishing Deadline for the Filing of General Administrative Expense Against the Debtors) Filed by NorthEast Gas Generation, LLC.Filed Dec 22, 2020Dec 22, 2020
- Dkt. 412Order GRANTING Motion For Final Decree (A) Closing the Chapter 11 Case of Northeast Gas Generation, LLC and (B) Terminating Claims and Noticing Services(related document(s)((403),(411)) Signed on 3/22/2021.Filed Mar 22, 2021Mar 22, 2021