VWS Holdco Converts to Chapter 7 After $183M Insider Debt and Failed Landfill Sale
ElevenFlo ·
VWS Holdco and Shoosmith Bros. are in Chapter 7 following conversion and transfer of their cases from Delaware to the Eastern District of Virginia on July 31, 2025. The notice of receipt Dkt. 230 records the transfer for administration in Virginia; the conversion order requires a debtor representative to attend the creditors’ meeting.
Jump to section
VWS Holdco, Inc. and its subsidiary Shoosmith Bros., Inc. ran a chapter 11 case for just 60 days before obtaining conversion to chapter 7 liquidation Dkt. 228 and transferring venue Dkt. 229 from Delaware to the Eastern District of Virginia, abandoning a DIP-backed sale of a closed Virginia municipal solid waste landfill. The debtors filed their petitions on June 1, 2025 in the U.S. Bankruptcy Court for the District of Delaware (No. 25-10979, jointly administered), reporting roughly $183 million of insider-held note debt Dkt. 12 against minimal assets after the Shoosmith Landfill stopped accepting waste in December 2022. Court filings state that a former employee allegedly falsified reports on landfill leachate, triggering termination of a disposal contract with Chesterfield County and an eleven-fold jump in treatment costs law360.com: an eleven-fold jump in treatment costs (outside source, not verified by ElevenFlo) for a facility that still generates about 400,000 gallons of leachate weekly chesterfield.gov: 400,000 gallons of leachate weekly (outside source, not verified by ElevenFlo).
| Debtor(s) | VWS Holdco, Inc. (2 jointly administered entities) |
| Court | U.S. Bankruptcy Court, District of Delaware (transferred to E.D. Virginia) |
| Case Number | 25-10979 (jointly administered) |
| Judge | Hon. J. Kate Stickles |
| Petition Date | June 1, 2025 |
| Conversion to chapter 7 | July 31, 2025 |
| Venue Transfer | July 31, 2025 (to E.D. Virginia) |
| Total Prepetition Debt | about $183 million (insider-held notes) |
| Scheduled Assets / Liabilities | $0–$50,000 / $100–$500 million |
| DIP Facility | Up to $5.4 million (Volunteer Enterprises); interim only, never finalized |
| Surety Bonds | about $19.3 million closure/post-closure (Evergreen) |
| Table: Case Snapshot |
Shoosmith Landfill and Insider Ownership Structure
The Shoosmith Landfill operated from 1976 until it stopped accepting waste in December 2022 Dkt. 12, on a site in Chester, Chesterfield County, Virginia, about ten miles south of Richmond. It accepted municipal solid waste, construction and demolition debris, and industrial waste under conditional use permits.
The current ownership structure dates to June 2008. Shoosmith Bros., Inc. owns and operates the landfill, while VWS Holdco, Inc. serves as the parent holding company. The First Day Declaration Dkt. 12 describes VWS Holdco as wholly owned by non-debtor VWS Acquisitions, LLC, which has three ownership constituencies: Environmental Services Management of Virginia, LLC (55.64% common units, 68.14% voting units), Volunteer Enterprises, LLC (41.36% common, 28.19% voting), and Larry McGee individually (3% common, 3.67% voting). Fred G. Nichols serves as president and Paul Lawrence McGee as vice president. Volunteer Enterprises—the proposed DIP lender—is owned 50/50 by Nichols and McGee, the same insider relationship that runs through the prepetition debt.
The landfill operates gas collection wells and flares locator.wastebits.com: gas collection wells and flares (outside source, not verified by ElevenFlo), leachate collection and storage systems, and groundwater monitoring installations. A February 2024 inspection by the Virginia Department of Environmental Quality chesterfield.gov: 400,000 gallons of leachate weekly (outside source, not verified by ElevenFlo) classified the facility as an Elevated Temperature Landfill, a designation indicating potential subsurface thermal activity under state regulations.
Insider-Held Notes and Bridge Financing
The debtors entered bankruptcy owing approximately $183.5 million in secured obligations held by insider-affiliated entities, comprising $24.7 million in Senior Notes, $158.4 million in Junior Notes, and $500,000 in Bridge Notes. The primary indebtedness arose under an Amended and Restated Securities Purchase Agreement Dkt. 12 dated April 30, 2020, under which VWS Holdco issued Senior Notes and Junior Notes in original principal amounts of $35.8 million and $64.9 million. The Senior Notes carry first-priority liens and the Junior Notes second-priority liens on substantially all of the debtors' assets.
Through a Non-Recourse Securities Assignment Agreement effective January 27, 2023, Volunteer Enterprises, LLC acquired the Notes and became the Notes Collateral Agent. Because Volunteer is owned equally by the debtors' president and vice president, the assignment consolidated the secured debt with company insiders, and Volunteer later proposed to serve as the DIP lender Dkt. 15. On May 27, 2025, days before the petition date, the parties executed a third amendment to the Securities Purchase Agreement creating the $500,000 Bridge Notes to fund bankruptcy preparation. The Bridge Notes carried liens ranking pari passu with the Senior Notes, and the debtors intended to roll them up into the DIP facility.
The Virginia Department of Environmental Quality required the debtors to maintain roughly $19.3 million in financial assurance for closure and post-closure obligations through two surety bonds issued by Evergreen National Indemnity Company: a closure bond of about $6.6 million and a post-closure bond of about $12.7 million. To secure those bonds, Evergreen holds approximately $14.7 million in cash collateral, a portion of the debtors' remaining liquid assets, as described in the First Day Declaration Dkt. 12.
Expansion Denial, Gas Royalties, and Leachate Costs
The bankruptcy followed a series of operational and regulatory issues described in court filings.
Blocked expansion, 2016–2018. An adjacent rock quarry operated by Vulcan Materials was scheduled for conversion to roughly 30 million tons of additional airspace, and in February 2016 the Virginia DEQ issued a permit authorizing the use. Chesterfield County challenged the permit and blocked the expansion, and in July 2018 the county Board of Supervisors denied the land-use application for the conversion. Subsequent litigation against the county was unsuccessful. The First Day Declaration Dkt. 12 states that the denial forced the company to write off about 17 million tons of planned capacity. A 2004 Virginia Supreme Court case caselaw.findlaw.com: 2004 Virginia Supreme Court case (outside source, not verified by ElevenFlo) documented earlier disputes between the operator and the county.
Closure and lost revenue, December 2022. With expansion blocked and capacity exhausted, the landfill ceased accepting waste on December 30, 2022 Dkt. 12, ending the debtors' primary revenue stream while environmental obligations continued. The debtors downsized staff and retained consultants for the closure process, which—managed by related entity Shoosmith Construction—includes placing intermediate and final cover, repairing erosion damage, cleaning sediment basins, replacing storm piping, and installing slope down drains. Property transfers in 2024 reduced the landfill footprint from 506 to 335 acres and cut permitted design capacity from 75.89 million to 42.1 million cubic yards.
The Swift Creek Renewables gas contract. In April 2020, Shoosmith Bros. contracted with Morrow Energy, through subsidiary Swift Creek Renewables, LLC ("SCR"), to capture, treat, and sell landfill methane through pipeline networks; the gas qualifies for special treatment under federal policy for its cellulosic renewable value, as described in the First Day Declaration. To enable SCR's operations, Shoosmith purchased gas rights from Ingenco Dkt. 12 (now owned by Archaea Energy, a BP company) for $6.75 million, structured as sixty-four monthly payments of $126,682.20, with the first gas transfer on September 13, 2023.
Royalties below projection. The SCR transaction entitled Shoosmith to a 25% royalty on gas production, with projections exceeding $1.0 million per month. A contractual provision halved royalties until SCR recovered "Reimbursable Costs" estimated not to exceed $8.0 million. Actual results differed sharply, according to the CRO's declaration Dkt. 12:
| Metric | Projected | Actual |
|---|---|---|
| SCR Construction Costs | about $40 million | Higher |
| Reimbursable Costs Cap | $8 million | $42+ million |
| Monthly Royalty | $1+ million | <$50,000 |
| February 2025 Royalty (paid May) | — | $44,379 |
| March 2025 Royalty (due June) | — | about $13,920 |
Because reimbursable costs reached more than $42 million Dkt. 12 against the $8 million cap, royalties stayed reduced far longer than anticipated, holding post-closure revenue below $50,000 per month.
Environmental violations, June 2024. On June 20, 2024, Shoosmith received a letter from the Virginia DEQ Dkt. 12 asserting violations of Air Pollution Control Law, including high-temperature wells, destruction of the synthetic closing cap's integrity, and leachate generation exceeding engineering estimates. Shoosmith contends that SCR caused these conditions through the manner in which it drilled the landfill liner during methane capture, allegations that remain disputed.
Leachate contract termination, July 2024. Effluent leachate—the contaminated liquid generated when precipitation percolates through decomposing waste—requires continuous removal and treatment. Until July 3, 2024, Shoosmith held a contract with Chesterfield County Dkt. 12 to treat leachate at the county's Publicly Owned Treatment Works for $0.02 per gallon, keeping monthly treatment costs between $30,000 and $50,000. According to the First Day Declaration, a former employee allegedly falsified the quantity and chemical analysis of the leachate delivered to the county, triggering suspension and termination of the contract. Forced to use private providers, the debtors now pay $0.22 per gallon ($0.15 treatment plus $0.07 transportation), an "eleven-time cost increase" the debtors called unsustainable given that they "now have relatively no income." The landfill generates about 400,000 gallons of leachate weekly, or roughly 20.8 million gallons annually, pushing annual treatment costs above $597,000 against a 2017 estimate of about $18,950 that county documents note chesterfield.gov: 400,000 gallons of leachate weekly (outside source, not verified by ElevenFlo) the company has not updated.
The 60-Day Chapter 11 Case
VWS Holdco, Inc. and Shoosmith Bros., Inc. filed voluntary chapter 11 petitions Dkt. 1 on June 1, 2025, in the U.S. Bankruptcy Court for the District of Delaware. Steven F. Agran of Carl Marks Advisory Group LLC, retained as Chief Restructuring Officer three days earlier on May 29, 2025, submitted the First Day Declaration Dkt. 12. The debtors stated two purposes for the filing: addressing the Swift Creek Renewables contract and leachate-removal issues, and initiating a sale to preserve value and provide for continued operation and closure under a new owner. They later moved to reject the SCR executory contract Dkt. 85 and sought standard first-day relief, including joint administration Dkt. 3, cash management Dkt. 5, employee wages Dkt. 6, insurance and surety bond maintenance Dkt. 7, utility service protection Dkt. 8, and critical vendor payment authority Dkt. 10.
DIP financing never finalized. The proposed DIP lender, Volunteer Enterprises, LLC, was the same insider entity that held the prepetition Senior and Junior Notes. The DIP motion Dkt. 15, filed June 2, 2025, proposed a senior secured superpriority term loan of up to $5.4 million—$4.9 million in new money plus a $500,000 roll-up of the Bridge Notes—with $1.8 million on the initial interim draw, Volunteer acting as DIP agent, and a 13-week budget tied to the sale milestones. The court entered an interim DIP order Dkt. 42 on June 4 and a second interim order Dkt. 146 on July 2, but no final DIP order was ever entered.
Chesterfield County and the Virginia DEQ filed a joint objection Dkt. 189 to the final DIP order on July 24, 2025, the same day the debtors moved to convert, raising concerns about the financing structure's environmental implications. The Official Committee of Unsecured Creditors also objected Dkt. 193, arguing the DIP served as an insider-protection device rather than a value-maximizing bridge. The committee alleged that the debtors' directors had extracted more than $31 million in the year before the petition date, including about $29.88 million in cash payments to Volunteer, and that the DIP budget allocated only $200,000 to committee professionals against roughly $2.15 million for debtor professionals. It also challenged liens on avoidance-action proceeds and broad releases for insiders and related parties.
Interrupted sale process. The debtors retained Teneo Securities LLC teneo.com: Teneo Securities LLC (outside source, not verified by ElevenFlo) as investment banker to market substantially all assets. The bidding procedures order Dkt. 139, entered July 1, 2025, contemplated a stalking-horse framework with a break-up fee of up to 3% and expense reimbursement of up to $150,000, a July 28 bid deadline, an August 4 auction, and an August 20 sale hearing. The sale motion Dkt. 67 and sale hearing notice Dkt. 151 had been filed in June and early July, but the conversion to chapter 7 ended the process before any transaction closed.
Committee formation. The Official Committee of Unsecured Creditors was appointed Dkt. 79 and retained Greenberg Traurig, LLP gtlaw.com: Greenberg Traurig, LLP (outside source, not verified by ElevenFlo) as counsel. The committee's involvement was brief: its counsel's retention was approved Dkt. 220 on July 30, 2025, one day before conversion.
Conversion and Venue Transfer
Fifty-three days after filing, the debtors themselves moved to convert Dkt. 234 the case to chapter 7 liquidation on July 24, 2025, supported by a declaration listed in the certificate of service Dkt. 234 and a motion to shorten notice Dkt. 196. The motion came from the debtors rather than from creditors or the U.S. Trustee. The court entered the conversion order Dkt. 228 on July 31, 2025.
The same day, Chesterfield County filed a joint motion to transfer venue, later granted by the court Dkt. 229 to the Eastern District of Virginia, joined by the Virginia DEQ Dkt. 190, surety issuer Evergreen National Indemnity Company Dkt. 215, and Swift Creek Renewables Dkt. 214. The court entered the order transferring venue Dkt. 229 on July 31, contemporaneously with the conversion order, and the record transferred Dkt. 230 on August 1. The transfer placed the chapter 7 case in the federal district encompassing Chesterfield County, where the landfill is located and environmental compliance obligations remain.
Professional Retentions
The debtors retained Pashman Stein Walder Hayden, P.C. pashmanstein.com: Pashman Stein Walder Hayden, P.C. (outside source, not verified by ElevenFlo) as bankruptcy counsel, Carl Marks Advisory Group LLC carlmarksadvisors.com: Carl Marks Advisory Group LLC (outside source, not verified by ElevenFlo) as chief restructuring officer (Steven F. Agran), and Teneo Securities LLC as investment banker. Verita Global (Kurtzman Carson Consultants, LLC) served as claims and noticing agent. The Official Committee of Unsecured Creditors retained Greenberg Traurig, LLP as counsel.
Post-Closure Environmental Obligations
A debtor in possession must continue to comply with environmental rules during chapter 11, including air emissions, water discharge, and hazardous waste requirements, and responsible parties bear liability for remediation costs bradley.com: bear liability for remediation costs (outside source, not verified by ElevenFlo) under CERCLA. Post-closure monitoring waste360.com: Post-closure monitoring (outside source, not verified by ElevenFlo) can run 30 years or more after a landfill stops accepting waste, so the Shoosmith facility, closed in December 2022, carries compliance obligations into the 2050s.
For Shoosmith, the Elevated Temperature Landfill designation, documented integrity failures in the synthetic cap, and roughly 400,000 gallons of weekly leachate drive those obligations. The $19.3 million in surety bonds Dkt. 12, backed by $14.7 million in cash collateral held by Evergreen, provides the financial assurance for closure and post-closure work. The facility's elevated-temperature status falls under tightening methane requirements wastedive.com: tightening methane requirements (outside source, not verified by ElevenFlo) that add to operators' compliance costs.
Frequently Asked Questions
What caused VWS Holdco's bankruptcy? The bankruptcy followed multiple factors: the 2018 denial of expansion permits that eliminated future capacity; closure in December 2022 that ended revenue; the gas royalty arrangement with Swift Creek Renewables producing lower-than-projected income; a June 2024 environmental violation notice; and the termination of a leachate disposal contract with Chesterfield County after a former employee allegedly falsified testing reports.
Why did leachate costs increase so much? Prior to July 2024, the debtors paid Chesterfield County $0.02 per gallon for leachate treatment. After termination of the county contract over falsified reports, private treatment providers charged $0.22 per gallon including transportation—an eleven-fold increase the debtors characterized as unsustainable given their lack of revenue.
Why was the case converted to chapter 7? The debtors themselves moved to convert the case on July 24, 2025, just 53 days after filing. The conversion order was entered July 31, 2025, after interim DIP approval but before any sale closed.
Why was venue transferred to Virginia? The venue moved to the Eastern District of Virginia, the district encompassing Chesterfield County where the landfill sits. Chesterfield County, the Virginia DEQ, and surety issuer Evergreen all supported the transfer.
How much debt did the debtors have? The debtors entered bankruptcy with about $183.5 million in prepetition secured debt: $24.7 million in Senior Notes, $158.4 million in Junior Notes, and $500,000 in Bridge Notes, all held by insider-affiliated entities.
Who is the claims agent for VWS Holdco? Verita Global (Kurtzman Carson Consultants) served as the claims and noticing agent. The conversion order relieved Verita of most noticing responsibilities as of the July 31, 2025 conversion date, subject to local-rule compliance in the transferred chapter 7 case.
Ask our AI chat to review the VWS Holdco docket, including the key filings, orders, and deadlines behind this case. For docket monitoring and AI research access, see ElevenFlo pricing.
For related ElevenFlo coverage of resource and energy liquidations with environmental obligations, see Blackjewel's chapter 11 coal liquidation, Alpine Summit Energy Partners' liquidating plan after asset sales, and Aleon Metals' 52-day 363 sale. Browse the full ElevenFlo bankruptcy coverage library for additional case studies.
Sources
- Dkt. 1Chapter 11 Voluntary Petition of VWS Holdco, Inc.. Fee Amount $1738. Filed by VWS Holdco, Inc.. (Weiss, John) (Entered: 06/01/2025)Filed Jun 1, 2025Jun 1, 2025
- Dkt. 3Joint Administration MotionFiled Jun 1, 2025Jun 1, 2025
- Dkt. 5Cash Management MotionFiled Jun 1, 2025Jun 1, 2025
- Dkt. 6Wages MotionFiled Jun 1, 2025Jun 1, 2025
- Dkt. 7Insurance and Surety MotionFiled Jun 1, 2025Jun 1, 2025
- Dkt. 8Utilities MotionFiled Jun 1, 2025Jun 1, 2025
- Dkt. 10Critical Vendors MotionFiled Jun 1, 2025Jun 1, 2025
- Dkt. 12Declaration in Support of First Day ReliefFiled Jun 1, 2025Jun 1, 2025
- Dkt. 15DIP Financing MotionFiled Jun 2, 2025Jun 2, 2025
- Dkt. 42Interim DIP Financing OrderFiled Jun 4, 2025Jun 4, 2025
- Dkt. 67Asset Sale and Bidding Procedures MotionFiled Jun 11, 2025Jun 11, 2025
- Dkt. 79Appointment of Unsecured Creditors' CommitteeFiled Jun 16, 2025Jun 16, 2025
- Dkt. 85Motion to Reject Swift Creek Renewables ContractFiled Jun 18, 2025Jun 18, 2025
- Dkt. 139Bidding Procedures OrderFiled Jul 1, 2025Jul 1, 2025
- Dkt. 146Second Interim DIP OrderFiled Jul 2, 2025Jul 2, 2025
- Dkt. 151Notice of Asset Sale and AuctionFiled Jul 3, 2025Jul 3, 2025
- Dkt. 189Objection to DIP Financing MotionFiled Jul 24, 2025Jul 24, 2025
- Dkt. 190Joinder (related document(s)[189]) Filed by Virginia Department of Environmental Quality. (Kulbok, Katherine)Filed Jul 24, 2025Jul 24, 2025
- Dkt. 193UCC Objection to DIP MotionFiled Jul 24, 2025Jul 24, 2025
- Dkt. 196Motion to Shorten NoticeFiled Jul 24, 2025Jul 24, 2025
- Dkt. 214Joinder to Motion to Transfer VenueFiled Jul 29, 2025Jul 29, 2025
- Dkt. 215Joinder of Evergreen National Indemnity Company in Joint Motion of Chesterfield County, Virginia and The Virginia Department of Environmental Quality to Transfer Venue to The United States Bankruptcy Court for The Eastern District of Virginia (related document(s)[198]) Filed by Evergreen National Indemnity Company. (Rosner, Frederick)Filed Jul 29, 2025Jul 29, 2025
- Dkt. 220Order Retaining Committee CounselFiled Jul 30, 2025Jul 30, 2025
- Dkt. 228Order Converting Cases to Chapter 7Filed Jul 31, 2025Jul 31, 2025
- Dkt. 229Order Transferring VenueFiled Jul 31, 2025Jul 31, 2025
- Dkt. 230Notice of Venue Transfer ReceiptFiled Aug 1, 2025Aug 1, 2025
- Dkt. 234Certificate of Service re Documents Served on July 24, 2025 (related document(s)[194], [196], [197], [199]) Filed by Kurtzman Carson Consultants, LLC dba Verita Global. (Kass, Albert)Filed Aug 6, 2025Aug 6, 2025
- Weban eleven-fold jump in treatment costslaw360.com · Outside source, not verified by ElevenFlo
- Web400,000 gallons of leachate weeklychesterfield.gov · Outside source, not verified by ElevenFlo
- Webgas collection wells and flareslocator.wastebits.com · Outside source, not verified by ElevenFlo
- Web2004 Virginia Supreme Court casecaselaw.findlaw.com · Outside source, not verified by ElevenFlo
- WebTeneo Securities LLCteneo.com · Outside source, not verified by ElevenFlo
- WebGreenberg Traurig, LLPgtlaw.com · Outside source, not verified by ElevenFlo
- WebPashman Stein Walder Hayden, P.C.pashmanstein.com · Outside source, not verified by ElevenFlo
- WebCarl Marks Advisory Group LLCcarlmarksadvisors.com · Outside source, not verified by ElevenFlo
- Webbear liability for remediation costsbradley.com · Outside source, not verified by ElevenFlo
- WebPost-closure monitoringwaste360.com · Outside source, not verified by ElevenFlo
- Webtightening methane requirementswastedive.com · Outside source, not verified by ElevenFlo