ESML Holdings’ July 8, 2016 Chapter 11 case was closed on July 7, 2025, under a final decree Dkt. 1977, following the 2017 effectiveness of its reorganization plan. The decree preserves the litigation trustees’ ability to seek reopening for specified purposes and does not affect pending adversary proceedings.
ESML Holdings’ Chapter 11 case, filed on July 8, 2016, was closed on July 7, 2025, when the court entered a final decree Dkt. 1977 closing the cases of ESML Holdings and its subsidiary, Essar Steel Minnesota LLC, now Mesabi Metallics Company LLC.
The debtors were developing an integrated iron ore pellet project in Minnesota’s Mesabi Range. Their first-day declaration Dkt. 14 described halted construction, debt defaults, the termination of a major offtake agreement, and a threatened termination of mineral leases as drivers of the filing.
The court confirmed the reorganization plan Dkt. 1025 on June 13, 2017, and the debtors’ effective-date notice Dkt. 1398 reported that the plan became effective on December 22, 2017. Before closure, Cleveland-Cliffs objected that its lease-rejection claim remained unresolved; the final decree Dkt. 1977 addressed the treatment of specified payments on that claim, preserved rights to dispute claims, and left pending adversary proceedings unaffected. It also permits the litigation trustees to seek reopening to extend the trusts’ terms or for other cause.
Sources
- Dkt. 14First Day DeclarationFiled Jul 8, 2016Jul 8, 2016
- Dkt. 1025Findings of Fact, Conclusions of Law and Order Confirming the Third Amended Chapter 11 Plan of Reorganization for Mesabi Metallics Company LLC (f/k/a Essar Steel Minnesota LLC) and ESML Holdings Inc. Proposed by the Drbtors (related document(s)[690], [691], [791], [792], [793], [794], [795], [808], [809], [810], [811], [814], [817], [918], [919], [956], [957], [960], [961], [962], [990], [991], [992], [993], [999], [1000], [1002], [1003], [1005], [1009], [1010], [1012], [1022]) Signed on 6/13/2017. (Attachments: # (1) Exhibit A # (2) Exhibit B) (MML)Filed Jun 13, 2017Jun 13, 2017
- Dkt. 1398Notice of Effective Date /Notice Of (I) Entry Of Order Confirming Third Amended Chapter 11 Plan Of Reorganization For Mesabi Metallics Company LLC (f/k/a Essar Steel Minnesota LLC) And ESML Holdings Inc.; (II) Occurrence Of Effective Date; And (III) Bar Date For Administrative Claims, Fee Claims And Rejection Damage Claims (related document(s)[990], [1025], [1034], [1057], [1160], [1168], [1176], [1231], [1355], [1358], [1362]) Filed by ESML Holdings Inc.. (Schlerf, Jeffrey)Filed Dec 22, 2017Dec 22, 2017
- Dkt. 1977Final Decree Closing Chapter 11 CasesFiled Jul 7, 2025Jul 7, 2025